The walls are going up at the new
George Brown campus-with-a-view.
Senior project manager Nerys Rau says the concrete work on the Waterfront campus, next to Corus Quay and Sugar Beach, was finished in July. The structural steel is all up, and the curtain wall is now filling in.
"We’re complete to the second floor on the east side and probably even higher on the west side," she says.
The 320,000-square-foot, $175-million single-building project is set to be substantially completed by July 2012, and to open for students in September.
The parking garage, which is 75 per cent funded and owned by
Waterfront Toronto, is mostly complete and is being painted.
Writer: Bert Archer
Source: Nerys Rau