As the East Bayfront grows, Waterfront invests in making it cycle-friendly.



Waterfront Toronto is not satisfied to wait until the East Bayfront is finished before opening it up to cyclists. It wants them there now.

And so they’re building an interim cycling infrastructure (and one for pedestrians as well), that will serve the burgeoning area until development and funding are in place.

East Bayfront was a formerly industrial part of the waterfront,” says Waterfront spokeswoman Sam Gileno. “It lacked basic infrastructure such as a continuous sidewalk on the south side of the street. The full revitalization of Queens Quay in this area is dependent on funding for the East Bayfront LRT. The interim pedestrian and cyclists improvements will help connect the area until funding for this important transit line is in place and construction is complete.”

According to Gileno, there are two major projects getting underway.

First is a cyclist network.

“We will create a continuous off-street Martin Goodman Trail on the south side of Queens Quay which will separate cyclists from motor vehicles along the waterfront,” she says. “By spring, 2015, when both this project and the revitalization of Queens Quay are complete, the Martin Goodman Trail will be in place from Bathurst Street all the way to Parliament Street.”

The second is a continuous sidewalk for pedestrians.

“Currently the sidewalk in this area is an asphalt path,” she says. “It will be replaced with a city standard concrete sidewalk with landscaping alongside. A north-south pedestrian crosswalk will also be added along the east side of the Parliament Street intersection.”

The two will cost $1.8 million, which includes both hard and soft costs, and will remain in place until Queens Quay has been fully renovated.

Writer: Bert Archer
Source: Sam Gileno